February 13, 2009 - The sand and blocks are here (I feel like Steve Martin in "The Jerk")!!
 
   

February 15, 2009 - The first day of laying block is finally here.  Roger Holiman and his helper started very early.  They are hard at work when we arrive.  Talk about hard work....lifting all of those blocks....I'm very impressed.  While they're busy laying block, Don and Cricket are busy killing weeds/vines and I'm the official Project Photographer.

February 16, 2009 - The second day of laying block - WOW!  What a difference a day makes! It's actually beginning to look like a house.  We could really see where rooms were going to be!  They had planned to be finished with the block by tomorrow (Tuesday)....but, they don't think they're going to make it.  Maybe Thursday.

WE'RE MOVIN' ON UP!!